Farm solar grid connection in Scotland: DNO applications and G99

Quick answer

How does farm solar connect to the grid in Scotland?

Most farm solar systems need approval from the local network operator before they connect: SPEN in central and southern Scotland, or SSEN in the north and islands. Systems above about 3.68kW per phase need a G99 application. Where the rural grid is constrained, export-limited or zero-export designs still let you use your solar.

Last updated: 30 October 2026

Overhead power line and pole-mounted transformer beside a stone farm steading with solar panels in the field

Key facts

Last updated: 30 October 2026
  • SPEN covers central and southern Scotland; SSEN covers the north and Highlands
  • Systems above 3.68kW per phase need a G99 application before connection
  • G98 covers small systems up to 16A per phase — notified after installation
  • Rural Scottish networks often have limited spare export capacity
  • Zero-export designs use Engineering Recommendation G100
  • Batteries must be included in the grid application
  • Last updated: 30 October 2026

Why grid connection matters

Any generator connected to your supply, including solar panels and batteries, can affect the local network. Network operators, known as DNOs, must know about it and, for larger systems, approve it first. Rural Scottish networks often run on long overhead lines with limited spare capacity, so the grid can shape what size of system is possible and how it is designed.

G98 or G99?

G98: small systems

Engineering Recommendation G98 covers systems up to 16A per phase, roughly 3.68kW on single-phase or 11.04kW on three-phase. These are notified to the DNO after installation. A few small farm systems fall into this category.

G99: larger systems

Anything above those limits, which includes most farm systems, needs a G99 application. The DNO reviews your supply, the local network and the proposed system, then accepts it, accepts it with conditions such as an export limit, or asks for further studies. Connection must not go ahead until approval is in place.

Steel electricity pylons and overhead power lines crossing open green farmland
Larger roof and field arrays almost always need G99 approval before they are switched on.

What goes into the application

  • Your supply details, including MPAN, supply capacity and whether it is single or three-phase.
  • The inverter and battery specifications, with their certification.
  • A single-line diagram of the proposed system and how it connects to your board.
  • The maximum export you are asking for, or confirmation of export limitation.

We prepare and submit this on your behalf and deal with any questions from the network operator.

When the grid is full: export limits and zero export

If the local network cannot take your full output, the DNO may offer a lower export limit, or a reinforcement cost to increase capacity. Often a better answer is an export-limited or zero-export design, where the inverter is set to match on-site demand so little or nothing flows back to the grid. This is covered by Engineering Recommendation G100 and can avoid long reinforcement delays.

Zero export still pays: the main value of farm solar is electricity you use yourself. Adding battery storage lets you keep more of the surplus that cannot be exported.

Timescales

G99 approval is often the longest single step in a farm solar project. Timescales depend on the network operator, the size of the system and how much spare capacity the local network has. Where studies or network works are needed, it can take considerably longer, which is why we apply early and set out the expected programme in your quote.

Next steps

See how system size is chosen in our farm solar sizing guide, compare roof and ground-mounted options, and read about farm solar finance. Quick answers are in the farm solar FAQ.

Get a quote

Frequently asked questions

Who is my network operator in Scotland?

SP Energy Networks (SPEN) covers central and southern Scotland, and Scottish and Southern Electricity Networks (SSEN) covers the north, the Highlands and the Islands. Your electricity bill or meter details confirm which applies to your farm.

When do I need a G99 application instead of G98?

G98 covers small systems up to 16A per phase, roughly 3.68kW on a single-phase supply or 11.04kW on three-phase, and is a notification after installation. Anything larger, which includes most farm systems, needs a G99 application and approval from the network operator before connection.

How long does a G99 application take?

It varies by network operator, system size and how busy the local network is. Where studies or reinforcement are needed, it can take considerably longer. Submitting early, alongside the design, keeps the overall project moving.

What is a zero-export solar system?

A system whose inverter is set so that little or no electricity flows back to the grid. It matches generation to on-site demand and is covered by Engineering Recommendation G100. It can let a farm install solar where the local network has no spare export capacity.

Do batteries need to be included in the grid application?

Yes. Battery inverters count towards the total generating capacity at your site, so they must be included in the G98 notification or G99 application. Adding a battery later usually means updating the application with the network operator.

Every project is assessed individually and you receive a fixed written quote before any work starts. Last updated: 30 October 2026.

Get your farm solar assessment.

Send us your latest electricity bill and we will model your usage, roof or land area, and likely system size. No site visit needed for the first conversation, and no pressure to proceed.

Desktop assessment from your bill, with no obligation
Fixed-price quote, not an estimate range
We install through MCS-certified partners
Property type

We will respond within one working day. See our privacy policy and cookie policy.